Roger the one pictured is a Transmig 300 and the electronics are cactus, also there are quite a few others in the same condition.
I do reckon going with that E-core I already have and that's one you and Mike have seen just to see if the E-core will work as a toriod replacement. A while ago we did work out for that one 300 turns are needed for the secondary and by 1.6mm wire I can go 2 inhand 1.6mm for 6 layers which will still leave plenty of room for the primary.
Now I did try to compare my old Kipoint inverter for standby current but with that inverter with no load it just went into fault mode and I did see 0.7 amps before the beeping started.
This weekend I'll be putting that new inverter inline for my shed power and I do need to put some round lugs on the end of the 240 volt wire cable that goes to my circuit breaker board so the inverter can hard wired into the shed.