GleamBright Regular Member
 Joined: 21/04/2025 Location: AustraliaPosts: 44 |
| Posted: 02:30am 23 Mar 2026 |
|
|
|
Thanks, in that case I'll have another look through my scrapped inverter components for toroids. I have the chokes from an Aerosharp but they're not suitable, from what I gather. The other builders may have to wear the costs, as they are planning to buy everything new, including primary toroid cores.
We'll hold on a conference call for now, but there may be some technical queries that would justify a voice contact and I'll get back to you if and when they arise.
So, the choke install isn't just 'plug and play', there is some pre commissioning testing required for each toroid? And if so, what equipment are we looking at? |